Improvement works at Tai O

Project Number:

7417RO
Attachment 1

Brief Description of Project Scope:

Phase 1 works include:

Phase 2 Stage 1 works include:

Phase 2 Stage 2 works include:

Remaining works:

Project Office in Civil Engineering and Development Department:

Sustainable Lantau Office (Enquiry: 2231 4408)

Consultant:

Mannings (Asia) Consultants Limited and Meinhardt Infrastructure and Environment Limited

Approved Project Estimate:

$151 million (Phase 1 works)
$124 million (Phase 2 Stage 1 works)
$813 million (Others)

Status:

Completed (Phase 1 works)
Completed (Phase 2 Stage 1 works)
Under Detailed Design (Phase 2 Stage 2 works)
Under Planning (Remaining works)

Current Progress:

Construction for the Phase 1 works was completed under PWP Item 7435RO and the facilities were commissioned in mid 2014.

Construction for the Phase 2 Stage 1 works under PWP Item 7469RO commenced in September 2016 and was substantially completed in October 2019.

Phase 2 Stage 2 works are under detailed design stage.

The Remaining works are under planning and the scope is being reviewed.