Tender Reference :
Contract No.: GE/2025/20
Procuring Department :
Civil Engineering and Development Department
Subject :
Landslip Prevention and Mitigation Programme, New Territories East, Phase 1, Contract 3
Description :
The works mainly comprise upgrading of some 15 government slopes and retaining walls and natural terrain hazard mitigation works to some 12 natural hillside catchments in the New Territories East. The works are scheduled to commence in August 2026 and will take about 45 months to complete.
Contractor :
Pan Kee Construction Limited
Contractor's Address :
Unit 7, 3/F,
Block 2, Tak Fung Industrial Centre,
No. 168 Texaco Road,
Tsuen Wan, New Territories
Quantity :
Not Applicable
Awarded Sum (million) :
HK$ 182,130,000.00