Tender Reference :
Contract No.: ND/2024/05Procuring Department :
Civil Engineering and Development DepartmentSubject :
Kwu Tung North New Development Area, Remaining Phase: Improvement Works of Fanling Highway (Pak Shek Au Portion) and Associated WorksDescription :
The works mainly include:-
- site clearance and formation (including land decontamination works);
- widening of Fanling Highway (Chau Tau to Pak Shek Au Portion);
- modification of Castle Peak Road (Chau Tau Portion);
- construction of Pak Shek Au Interchange;
- modification of Pak Shek Au Bridge across Fanling Highway;
- construction of footbridge across Fanling Highway (Pak Shek Au Portion);
- extension of existing subways no. NS161 and NS161A;
- construction of associated works including water mains, drainage, retention tanks, sewerage works, roadworks, cycle tracks, footpaths, junction improvement, box culverts, slope works, retaining walls, street furniture, landscaping works, electrical and mechanical works and other ancillary works; and
- implementation of environmental mitigation measures (including noise barriers and low-noise road surfacing) and environmental monitoring works for the works mentioned above.
The works commenced in January 2026 and will take about 58 months to complete.