Tender Reference :

Contract No.: NL/2023/11

Procuring Department :

Civil Engineering and Development Department

Subject :

Tung Chung New Town Extension – Infrastructure Works at Tung Chung Valley, Phase 2

Description :

The works mainly include:

  1. Construction of Road L25, Road L26 and Road L28;
  2. Construction of sewage pumping station (Tung Chung Valley (West));
  3. Construction of village sewerage at Lam Che, Nim Yuen, Shek Lau Po, Mok Ka and Shek Mun Kap;
  4. Construction of sustainable urban drainage system, stormwater attenuation & treatment pond at Tung Chung Area 45C;
  5. Construction of polders;
  6. Construction of Tung Chung River Park (Phase 2);
  7. Reprovisioning of Shek Mun Kap Public Toilet and refuse collection point;
  8. Ancillary works including associated civil, geotechnical, drainage, sewerage, water supply, electrical and mechanical engineering and landscaping works; and
  9. Implementation of environmental mitigation measures for the works mentioned above.
The works commenced in March 2026 and would take about 43 months to complete. 

Contractor :

CCC-CCECC-CR11G Joint Venture

Contractor's Address :

7/F., High Fashion Centre, 1-11 Kwai Hei Street, Kwai Chung, New Territories, Hong Kong

Quantity :

Not Applicable

Awarded Sum (million) :

HK$792 million