Tender Reference :
Contract No.: NL/2023/10Procuring Department :
Civil Engineering and Development DepartmentSubject :
Tung Chung New Town Extension – Infrastructure Works at Tung Chung Valley, Yu Tung Road and Ma Wan ChungDescription :
The works mainly include:
-
Construction of Road L22 and Road L24;
-
Construction of 2 nos. sewage pumping stations (Ma Wan Chung and Tung Chung Valley (North));
-
Construction of village sewerage at Ma Wan Chung, Wong Nai Uk and Ngau Au;
-
Construction of Sustainable Urban Drainage System, stormwater attenuation & treatment ponds at Tung Chung Area 45E;
-
Ancillary works including associated civil, geotechnical, drainage, sewerage, water supply, electrical and mechanical engineering and landscaping works; and
-
Implementation of environmental mitigation measures for the works mentioned above.
The works commenced in October 2025 and would take about 43 months to complete.