Brief Description of Project Scope:

The project is for the construction of a dual two-lane highway approximately 4.2 km long connecting Tseung Kwan O (TKO) at Po Shun Road in the east with proposed Trunk Road T2 in Kai Tak Development in the west. About 2.6 km of the highway is in the form of tunnel. Tseung Kwan O – Lam Tin Tunnel (TKO-LT Tunnel) will meet the TKO external traffic demand as a result of continual development of TKO. TKO-LT Tunnel, together with the proposed Trunk Road T2 and Central Kowloon Route, will form the Route 6 which will provide an east-west express link between West Kowloon and TKO areas.


Approved Project Estimate:

About $15.1 billion


Related Website:

http://www.tko-ltt.hk


Current Progress:

Construction commenced in July 2016


Project Office in Civil Engineering and Development Department:

East Development Office (Enquiry : 2301 1367)


Consultant:

AECOM Asia Co. Ltd.


Contract:

Contract No. NE/2015/01
Scope: The works include construction of the main tunnel of the TKO-LT Tunnel, construction of tunnel portal facilities and ventilation building at TKO, construction of slip roads, branch tunnels, viaducts, Lam Tin Interchange, tunnel portal facilities, ventilation building and administration building at Kwun Tong, and implementation of the associated building, civil, structural, marine, electrical and mechanical, landscaping and environmental protection and mitigation works.
Commencement Date: 11 July 2016
Completion Date: mid 2021
Contract Sum: $8.731 billion
Contractor: Leighton-China State Joint Venture

Contract No. NE/2015/02
Scope: The works include reclamation of approximately 3 hectares at Junk Bay, construction of the dual two-lane Road P2 of approximately 800 m long with approximately 200 m of the depressed carriageway covered by landscape deck, and implementation of the associated building, civil, structural, marine, electrical and mechanical, landscaping and environmental protection and mitigation works.
Commencement Date: 29 July 2016
Completion Date: mid 2021
Contract Sum: $1.777 billion
Contractor: CRBC-Build King Joint Venture

Contract No. NE/2015/03
Scope: The works comprise construction of a 70m long and 10m wide covered footbridge spanning over Po Shun Road connecting Park Central and Tiu Keng Leng Sports Centre, and ancillary works including a passenger lift, footpath, drainage, retaining walls, landscaping works and electrical & mechanical works.
Commencement Date: 16 December 2016
Completion Date: mid 2019
Contract Sum: $66 million
Contractor: Wing Lee (SK) Construction Company Limited