Home > On-going Projects > Major Projects > Under Construction > Kowloon > Kai Tak development – Stage 3A & Stage 4 infrastructure works at north apron area of Kai Tak Airport

On-going Projects

7761CL
Kai Tak development – Stage 3A & Stage 4 infrastructure works at north apron area of Kai Tak Airport
Kai Tak development – Stage 3A & Stage 4 infrastructure works at north apron area of Kai Tak Airport Kai Tak development – Stage 3A & Stage 4 infrastructure works at north apron area of Kai Tak Airport

Brief Description of Project Scope:

Stage 3A - infrastructure comprises the construction of the following major items:
  1. new roads about 890 metres (m) in total length covering L1, Road L11 and a slip road linking Prince Edward Road East (PERE) to Road D1;
  2. a vehicular underpass about 225m long across PERE forming part of Road L1;
  3. a new pedestrian subway of about 205m long, and extension of an existing subway about 60m in total length, across PERE;
  4. modification and widening of existing roads in former Kai Tak Airport north apron area and San Po Kong area;
  5. associated footpaths, street lighting, traffic aids, drainage, sewerage, water mains, landscaping works and electrical and mechanical works; and
  6. provision of necessary environmental mitigation measures and implementation of an environmental monitoring and audit programme associated with the above works.

Stage 4 - infrastructure comprises the construction of the following major items:
  1. construction of about 1 630m long of new roads covering part of Road D2, Road L6 and Road L19;
  2. reconstruction and widening of sections of existing footpaths at Sung Wong Toi Road and To Kwa Wan Road;
  3. construction of two sewage pumping stations, about 2 000m long of twin rising mains and 2 300m long of gravity sewer;
  4. construction of stormwater drains including about 3 600m long of road drains and 430m long of box culverts;
  5. associated footpaths, street lighting, traffic aids, water mains and landscaping works; and
  6. provision of necessary environmental mitigation measures and implementation of an environmental monitoring and audit programme for the works associated with the above works.

Approved Project Estimate:

$2.255 billion


Current Progress:

Kai Tak Development - Stage 3A and Stage 4 - infrastructure works at north apron area of Kai Tak Airport commenced on 15 July 2013 and 19 September 2013 respectively. Stage 3A infrastructure works were substantially completed in June 2017 whereas Stage 4 infrastructure works are still under construction.


Project Office in Civil Engineering and Development Department:

East Development Office (Enquiry: 2301 1393)


Consultant:

Ove Arup & Partners Hong Kong Ltd and Aecom Asia Company Limited


Contract:

Contract No. KL/2012/02
Scope: same as project scope for Stage 3A above
Commencement Date: 15 July 2013
Completion Date: June 2017
Contract Sum: $918 million
Contractor: Build King Construction Limited

Contract No. KL/2012/03
Scope: same as project scope for Stage 4 above
Commencement Date: 19 September 2013
Completion Date: Q3 2018
Contract Sum: $793 million
Contractor: Kwan On Construction Company Limited