Hung Shui Kiu/Ha Tsuen New Development Area - Second Phase Development

Project Number:

7787CL, 7829CL, 7845CL and 7846CL

Brief Description of Project Scope:

Second Phase development

1.      Advance Works Phase 3 mainly covers–

(a)   site clearance and formation (including land decontamination works) of about 51 ha of land together with the provision of associated engineering infrastructure, to ready these formed land for subsequent development of public and private housing, community facilities, commercial and industrial premises and other uses, and for construction of the proposed infrastructure works in paragraph 2(b) below;

(b)   engineering infrastructure works including a primary distributor road, district distributor roads, local roads, sewerage (including pumping stations), drainage, water supply, landscaping, electrical and mechanical ("E&M") and associated works; and

(c)   environmental mitigation measures and the EM&A programme for the works in paragraphs 2(a) and 2(b) above.

2.      Stage 2 Works and related studies mainly cover –

(a)   site clearance and formation (including land decontamination works) of about 200 ha of land, together with the provision of associated engineering infrastructure, to ready these formed land for subsequent development of public and private housing, community facilities, commercial and industrial premises, the Green Transit Corridor (comprising the Environmentally Friendly Transport Services, footpaths and cycle tracks) and other uses, and for construction of the proposed infrastructure works in paragraph 3(b) below;

(b)   engineering infrastructure works including district distributor roads, local roads, revitalisation of existing channels, sewerage (including pumping stations), drainage (including pumping stations), water supply, landscaping, E&M and associated works;

(c)   environmental mitigation measures and the EM&A programme for the works in paragraphs 3(a) and 3(b) above; and

(d)   related studies covering the following areas –

(i) reviewing the overall public and private housing mix with a view to increasing the share of public housing in view of the latest policy direction;

(ii) reviewing infrastructure provisions to support the revised housing mix and examining the possibility of reprovisioning Tin Ying Road around its current location;

(iii) assessing the feasibility of green and smart initiatives including common utility tunnels for the entire New Development Area development; and

(iv) conducting an urban and green design study for the area around the riverside promenade along the revitalised Tin Shui Wai River Channel in the north-eastern extent of Hung Shui Kiu/Ha Tsuen (HSK/HT) New Development Area (NDA).

Project Office in Civil Engineering and Development Department:

West Development Office (Enquiry: 2158 5680)

Consultant:

Agreement No. CE 1/2020 (CE) - "Hung Shui Kiu/Ha Tsuen New Development Area Package A Works for Second Phase Development - Design and Construction"
- Ove Arup & Partners Hong Kong Limited

Agreement No. CE 71/2020 (CE) - "Hung Shui Kiu/Ha Tsuen New Development Area Package B Works for Second Phase Development - Design and Construction"
- Ove Arup & Partners Hong Kong Limited

Related Website:

https://www.hskhtnda.hk

Current Progress:

The detailed design of site formation and infrastructure works under HSK/HT NDA Second Phase development (i.e. Advance Works Phase 3 and Stage 2 Works) commenced in 2020 in phases for target completion of construction works by 2034.

Modification Works of MTR Emergency Access Point 26 in Tuen Mun is for the roadworks of the Hung Shui Kiu/Ha Tsuen New Development Area. The gazette under Railway Ordinance (Chapter 519) is first published on 18 November 2022 and the scheme is authorized on 23 February 2023. The related documents can be viewed at the link below.  

Other Related Information:

https://www.hskhtnda.hk/en/info-centre/#document

Gazette Date Subject
10 March 2023 &
17 March 2023

Modification Works of MTR Emergency Access Point 26 in Tuen Mun