Remaining Phase of Site Formation and Engineering Infrastructure Works at Kwu Tung North and Fanling North New Development Area - Detailed Design and Site Investigation

Project Number:

7828CL
Attachment 1Attachment 2

Brief Description of Project Scope:

The Remaining Phase Works mainly cover –

(a) site formation of about 247 hectares of land (including soil treatment works) in the Kwu Tung North (KTN) and Fanling North (FLN) New Development Area (NDA) for housing, community, commercial and other developments as well as engineering infrastructure works;

(b) engineering infrastructure works including Fanling Bypass (Western Section), Po Shek Wu Road Flyover, new interchanges together with widening of Fanling Highway for connection with KTN NDA, local roads, cycle tracks, drainage, sewerage, waterworks, pumping stations, fresh water and flushing water service reservoirs, and landscaping works; and

(c) implementing the environmental mitigation measures for the works mentioned in (a) to (b) above.

Project Office in Civil Engineering and Development Department:

North Development Office (Enquiry: 3547 1624)

Consultant:

Agreement No. CE 18/2019 (CE) - “Development of Fanling North New Development Area, Remaining Phase – Design and Construction”
- Atkins China Limited

Agreement No. CE 19/2019 (CE) - “Development of Kwu Tung North New Development Area, Remaining Phase – Design and Construction”
- AECOM Asia Company Limited

Agreement No. CE 20/2019 (HY) - “Improvement of Tai Tau Leng Roundabout and Fanling Highway (Kwu Tung Section) - Design and Construction”
- AECOM Asia Company Limited

Agreement No. CE 21/2019 (WS) - “Fresh Water and Flushing Water Service Reservoirs and Associated Works in Fanling North – Design and Construction”
- Black & Veatch Hong Kong Limited

Approved Project Estimate:

$30,167.9 million

Related Website:

https://www.ktnfln-ndas.gov.hk/en/

Current Progress:

Construction commenced in July 2024.

Contract:

Contract No. ND/2024/01 - Kwu Tung North New Development Area, Remaining Phase: Site Formation and Infrastructure Works (South)

Scope:

The works mainly comprise site formation of lands (including site clearance and land decontamination works) and ground investigation within Kwu Tung North New Development Area (KTN NDA); construction of at-grade roads within KTN NDA connecting to Castle Peak Road (Kwu Tung Section) and Fanling Highway; construction of a vehicular bridge connecting proposed Road L1 and Road L2; construction of footbridges at proposed Road P2; construction of noise barriers and low noise road surfacing; construction of common utility enclosure and associated works; construction of a visitor centre; and ancillary works including footpaths, cycle tracks, lighting, traffic aids, drainage, sewerage, water mains, district cooling mains, landscaping works, slope works and electrical and mechanical works.

Commencement Date:

23 August 2024

Completion Date:

Mid 2030

Contract Sum:

$4,107 million

Contractor:

Build King – Richwell Engineering Joint Venture

Contract No. ND/2024/03 - Kwu Tung North New Development Area, Remaining Phase: Improvement Works of Fanling Highway (Kwu Tung Portion) and Associated Works

Scope:

The works mainly comprise site clearance and formation (including land decontamination works); widening of Fanling Highway (Kwu Tung Portion); modification of Castle Peak Road (Kwu Tung Portion); construction of footbridges across Fanling Highway (Kwu Tung Portion); construction of Kwu Tung Interchange; modification of Kwu Tung Road and construction of Road L3; construction of associated works including water mains, drainage and sewerage works, roadworks, cycle tracks, footpaths, box culverts, junction improvement works, slope works, retaining walls, street furniture, landscaping works, electrical and mechanical works and other ancillary works; implementation of environmental mitigation measures (including noise enclosures, noise barriers and low-noise road surfacing) and environmental monitoring works for the works mentioned above; and installation of Traffic Control and Surveillance System and conduction of associated testing and commissioning of Fanling Highway (Pak Shek Au, Kwu Tung and Tai Tau Leng Portion).

Commencement Date:

14 August 2024

Completion Date:

Mid 2030

Contract Sum:

$4,833 million

Contractor:

China State - STEC Joint Venture

Contract No. ND/2024/04 - Kwu Tung North New Development Area, Remaining Phase: Improvement Works of Tai Tau Leng Roundabout and Po Shek Wu Road and Associated Works

Scope:

The works mainly include widening of Fanling Highway (Tsung Pak Long to Tai Tau Leng Roundabout Portion); modification of Tsung Pak Long local road; construction of footbridge across Fanling Highway (Tsung Pak Long Portion); construction of Po Shek Wu Road Flyover connected to Fanling Highway westbound; road improvements at Tai Tau Leng Roundabout and Po Shek Wu Road; extension of existing subways no. NS201 and NS201A; construction of footbridge and cycle track at Po Shek Wu Road across MTR East Rail Line; construction of associated works including water mains, drainage and sewerage works, roadworks, cycle tracks, footpaths, box culverts, junction improvement works, slope works, retaining walls, street furniture, landscaping works, electrical and mechanical works and other ancillary works; and implementation of environmental mitigation measures (including noise enclosures, noise barriers and low-noise road surfacing) and environmental monitoring works for the works mentioned above.

Commencement Date:

31 December 2024

Completion Date:

Mid 2030

Contract Sum:

$1,598 million

Contractor:

CW - CRCC (ND202404) Joint Venture

Contract No. ND/2024/06 - Fanling North New Development Area, Remaining Phase: Fresh Water and Flushing Water Service Reservoirs and Associated Works

Scope:

The works mainly comprise construction of a fresh water service reservoir, a flushing water service reservoir and associated site formation, geotechnical, roadworks, power supply, drainage and landscaping works; laying of about 5.7-kilometre-long fresh water mains and about 5.7-kilometre-long flushing water mains; installation of pumps and associated electrical and mechanical works within Shek Wu Hui Water Reclamation Plant constructed by the Water Supplies Department; and implementation of environmental mitigation measures for the works mentioned above.

Commencement Date:

30 July 2024

Completion Date:

Second half of 2027

Contract Sum:

$1,290 million

Contractor:

Wo Hing - Tsun Yip Joint Venture

Contract No. ND/2024/07 - Fanling North New Development Area, Remaining Phase: Site Formation and Infrastructure Works (East)

Scope:

The works mainly comprise site formation of lands and ground investigation within Fanling North New Development Area (FLN NDA); construction of at-grade roads connecting FLN NDA to Fanling Highway and associated junction/road improvements; construction of noise barriers and low noise road surfacing; construction of common utility enclosure and associated works; and ancillary works including footbridges, footpaths, cycle tracks, lighting, traffic aids, sewage pumping stations, drainage, sewerage, water mains, landscaping works, slope works and electrical and mechanical works.

Commencement Date:

14 August 2024

Completion Date:

First half of 2030

Contract Sum:

$ 3,570 million

Contractor:

Build King - Richwell Civil Joint Venture

Other Related Information:

Gazette Schemes and Plans

PWP Item No. 7828CL - Cap. 370
Remaining Phase of Site Formation and Engineering Infrastructure Works at Kwu Tung North New Development Area and Fanling North New Development Area Fanling North New Development Area (Road Works)
Notice under section 8(2) of Cap 370
iconfbNotice: View
iconfbScheme: Download
iconfbPlan: All
iconfbResumption Plan: Download
iconfbLocation Plan: View

PWP Item No. 7828CL - Cap. 358AL
Remaining Phase of Site Formation and Engineering Infrastructure Works at Kwu Tung North New Development Area and Fanling North New Development Area Fanling North New Development Area (Sewerage Works)
Notice under section 8(2) of Cap 370 as applied by section 26 of the Cap. 358AL
iconfbNotice: View
iconfbLocation Plan: All
iconfbResumption Plan: Download

PWP Item No. 7828CL - Cap. 370
Remaining Phase of Site Formation and Engineering Infrastructure Works at Kwu Tung North New Development Area and Fanling North New Development Area Kwu Tung North New Development Area (Road Works)
Notice under section 8(2) of Cap 370
iconfbNotice: View
iconfbScheme: Download
iconfbPlan: All
iconfbResumption Plan: Download
iconfbLocation Plan: View

PWP Item No. 7828CL - Cap. 358AL
Remaining Phase of Site Formation and Engineering Infrastructure Works at Kwu Tung North New Development Area and Fanling North New Development Area Kwu Tung North New Development Area (Sewerage Works)
Notice under section 8(2) of Cap 370 as applied by section 26 of the Cap. 358AL
iconfbNotice: View
iconfbLocation Plan: All
iconfbResumption Plan: Download

PWP Item No. 7828CL - Cap. 370
Remaining Phase of Site Formation and Engineering Infrastructure Works at Kwu Tung North New Development Area and Fanling North New Development Area Fanling Highway and Castle Peak Road (Kwu Tung Section), Tai Tau Leng Roundabout and Po Shek Wu Road (Road Works)
Notice under section 8(2) of Cap 370
iconfbNotice: View
iconfbScheme: Download
iconfbPlan: All
iconfbResumption Plan: Download
iconfbLocation Plan: View

PWP Item No. 7828CL - Cap. 358AL
Remaining Phase of Site Formation and Engineering Infrastructure Works at Kwu Tung North New Development Area and Fanling North New Development Area Fanling Highway and Castle Peak Road (Kwu Tung Section), Tai Tau Leng Roundabout and Po Shek Wu Road (Sewerage Works)