Cycle track between Tsuen Wan and Tuen Mun – Advance Works

Project Number:

7293RS
Attachment 1

Brief Description of Project Scope:

The scope of the project comprises:

  1. a new cycle track with footpath of about 2.3 kilometre (km) in length from Tsing Tsuen Bridge to Bayview Garden in Tsuen Wan;
  2. one entry/exit hub (near MTR Tsuen Wan West Station) and two resting stations (near Tsing Tsuen Bridge and Bayview Garden) with supporting facilities including cycle parking spaces, benches, and a toilet at the hub;
  3. modification of an existing footbridge to make way for the new cycle track;
  4. associated landscaping and ancillary works; and
  5. implementation of environmental mitigation measures for the works mentioned in (i) to (iv).

Project Office in Civil Engineering and Development Department:

West Development Office (Enquiry: 2417 6367)

Consultant:

Ove Arup & Partners Hong Kong Ltd

Approved Project Estimate:

$140.9 million

Current Progress:

Works commenced in September 2018.

Contract:

Contract No. TW/2017/01

Scope: Same as project scope above.
Commencement Date: 21 September 2018
Completion Date: Fourth quarter of 2020
Contract Sum: $79.74 million

Contractor:

Richwell Civil Joint Venture

Back