Cycle Tracks Connecting North West New Territories with North East New Territories – Sheung Shui to Ma On Shan section

Project Number:

7271RS
Attachment 1

Brief Description of Project Scope:

The project forms part of the NT Cycle Track Network which connects local cycle track networks in various new towns and is mainly for recreation purpose. The works under this project comprise the construction of new cycle tracks of approximately 5 km long from Fanling to Tai Po and improvement to selected existing artery cycle tracks in Sheung Shui, Fanling, Tai Po and Sha Tin together with the provision of supporting facilities.

Project Office in Civil Engineering and Development Department:

West Development Office (Enquiry: 2417 6367)

Consultant:

AECOM Consulting Services Limited

Approved Project Estimate:

$230 million

Current Progress:

Already open to public.

Contract:

Contract No. TP/2010/02

Scope: Construction of new cycle track from Fanling to Tai Po and improvement to selected existing artery cycle tracks in Sheung Shui, Fanling, Tai Po and Sha Tin.
Commencement Date: 25 May 2010
Completion Date: Early 2014
Contract Sum: $148.8 million
Contractor: China National Chemical Engineering Group Corp

Contract No. TP/2011/01

Scope: Construction of public toilet, cycle rental kiosks, first aids kiosks, pavilion, cycle parking areas, practicing areas, sitting out areas and associated works at the Hubs in Sheung Shui and Sha Tin.
Commencement Date: 29 June 2011
Completion Date: November 2013
Contract Sum: $40.07 million
Contractor: Grand View (Civil) Ltd