Cycle Tracks Connecting North West New Territories with North East New Territories – Tuen Mun to Sheung Shui section (Remaining)

Project Number:

7259RS
Attachment 1

Brief Description of Project Scope:

The project forms part of the NT Cycle Track Network which connects local cycle track networks in various new towns and is mainly for recreation purpose. The works under this project comprises:

(i) construction of a new cycle track (with footpath) of about 11 kilometres (km) in length from Kam Tin River in Yuen Long to Sheung Yue River in Sheung Shui;

(ii) construction of three cycle bridges ( across an existing nullah adjoining San Tin Tsuen Road in Yuen Long, San Tin Eastern Channel in Yuen Long and Shek Sheung River in Sheung Shui);

(iii) construction of two cycle subways (across Kam Pok Road and at Cross Boundary Shuttle Bus San Tin Terminus in Yuen Long);

(iv) construction of three resting stations (at Kam Pok Road, Ngau Tam Mei and San Tin of Yuen Long);

(v) construction of a public toilet at Ho Sheung Heung with sewage treatment facilities; and

(vi) associated landscaping, traffic aids, road lighting and other miscellaneous works.

Project Office in Civil Engineering and Development Department:

West Development Office (Enquiry: 2417 6367)

Consultant:

Mannings (Asia) Consultants Limited

Approved Project Estimate:

$890.90 million

Current Progress:

Works commenced in June 2016

Contract:

Contract No. YL/2015/01

Header Details
Scope: Same as project scope above.
Commencement Date: 30 June 2016
Completion Date: Mid-2020
Contract Sum: $509.30 million
Contractor: Sang Hing – Kuly Joint Venture
Back