Liantang/Heung Yuen Wai Boundary Control Point and associated works - site formation and infrastructure works
Project Number:
5019GB
Brief Description of Project Scope:
The project mainly comprises site formation of about 23 hectares of land for provision of Boundary Control Point (BCP) buildings and associated facilities, construction of about 11km long dual 2-lane Connecting Road linking up the BCP with Fanling Highway, design and construction of the Hong Kong Special Administrative Region portion of vehicular bridges and pedestrian bridge crossing Shenzhen River, associated diversion/modification works at existing local roads and junctions, drainage, sewerage, waterworks and landscaping works.
Project Office in Civil Engineering and Development Department:
North Development Office (Enquiry : 3547 1624)
Consultant:
AECOM Asia Co. Ltd.
Approved Project Estimate:
$25.0 billion
Related Website:
https://www.hywh.hk/en/home/
Current Progress:
Major works of the project have been completed. The Connecting Road (named as "Heung Yuen Wai Highway") opened to public on 26 May 2019.
Contract:
Contract No. CV/2012/08
Scope: |
The works include construction of a dual two-lane trunk road (with about 0.4km of at-grade road and 4.8km of tunnel) connecting the Fanling Interchange with the Sha Tau Kok Interchange, tunnel administration building and ventilation buildings, provision and installation of ventilation system, E&M works and building services, associated landscaping works, drainage / sewerage, waterworks, utilities and traffic engineering works. |
Commencement Date: |
20 December 2013 |
Completion Date: |
29 July 2019 |
Contract Sum: |
$10.314 billion |
Contractor: |
Dragages Hong Kong Limited |
Contract No. CV/2012/09
Scope: |
The works include the construction of an interchange with four viaducts near Kiu Tau, Fanling for the connecting road to the Boundary Control Point, widening of a section of the Fanling Highway of about 1 km long near the interchange, demolition of the existing Kiu Tau Vehicular Bridge, re-provisioning of the existing Kiu Tau Footbridge, realignment of the existing Tai Wo Service Road West and Tai Wo Service Road East, and associated slope, drainage, sewerage, water, and landscape works. |
Commencement Date: |
31 July 2013 |
Completion Date: |
22 October 2018 |
Contract Sum: |
$2.545 billion |
Contractor: |
Chun Wo Construction and Engineering Company Limited |
Contract No. CV/2013/03
Scope: |
The works include site formation of about 23 hectares of land for the development of the new BCP, diversion/modification of Lin Ma Hang Road, associated drainage, sewerage, waterworks, utilities and landscaping works. |
Commencement Date: |
11 April 2013 |
Completion Date: |
9 January 2016 |
Contract Sum: |
$510 million |
Contractor: |
Sang Hing Civil - Richwell Machinery JV |
Contract No. CV/2013/08
Scope: |
The works include construction of a 4.6 km long dual two-lane trunk road (with about 0.6km at grade roads, 3.3km viaducts and a 0.7km tunnel) connecting Sha Tau Kok Road Interchange to BCP, and the associated environmental mitigation measures, landscaping, drainage/sewerage, waterworks and utilities works. |
Commencement Date: |
24 June 2015 |
Completion Date: |
27 April 2022 |
Contract Sum: |
$6.518 billion |
Contractor: |
CRBC-CEC-KADEN Joint Venture |
Contract No. NE/2014/02
Scope: |
The works mainly include design, supply, delivery, installation, testing and commissioning of a traffic control and surveillance system for the connecting road linking up the Liantang/Heung Yuen Wai Boundary Control Point and the existing Fanling Highway. The system will mainly consist of computer systems, communication facilities, variable message signs and other traffic field equipment. |
Commencement Date: |
27 April 2016 |
Completion Date: |
31 March 2021 |
Contract Sum: |
$337 million |
Contractor: |
Siemens Limited |
Contract No. NE/2014/03
Scope: |
The works include construction of the Hong Kong Special Administrative Region portion of four vehicular bridges and one pedestrian bridge crossing Shenzhen River. |
Commencement Date: |
11 December 2015 |
Completion Date: |
20 February 2020 |
Contract Sum: |
$462 million |
Contractor: |
Kwan On-Richwell-SCG JV |
Environmental Monitoring and Audit Information:
http://www.lthywbcpema.com