West Kowloon Reclamation – main works (remainder) – footbridge at the junction of Sham Mong Road and Tonkin Street West in Sham Shui Po

Project Number:

7801CL
Attachment 1

Brief Description of Project Scope:


The scope of the project comprises:

  1. a covered four-span footbridge system at the junction of Sham Mong Road and Tonkin Street West, with length of each span ranging from about 46 metres (m) to 67 m (235 m long in total) and the clear width ranging from about 4.0 m to 4.7 m;
  2. six lifts, four covered escalators, two covered staircases and three direct connections linking the proposed footbridge system with future adjacent developments;
  3. associated road works and ancillary works including a temporary covered staircase, footpaths, drainage, utilities, electrical and mechanical and landscaping works; and
  4. necessary environmental mitigation measures.

Project Office in Civil Engineering and Development Department:

South Development Office (Enquiry: 2301 1486)

Consultant:

Mott MacDonald Consultants (Hong Kong) Limited

Approved Project Estimate:

$368.9 million

Current Progress:

The works commenced on 28 September 2016 and are on schedule.

Contract:

Contract No. KL/2016/01

Scope: Same as project scope above
Commencement Date: 28 September 2016
Completion Date: Q3 2019
Contract Sum: About $222 million
Contractor: Wang Kee Construction Company Limited