Advance Site Formation and Engineering Infrastructure Works at Kwu Tung North and Fanling North New Development Areas

Project Number:

7747CL
Attachment 1Attachment 2

Brief Description of Project Scope:

The project is part of the first phase of the Kwu Tung North (KTN) and Fanling North (FLN) New Development Area (NDA) development and comprises mainly:   

  1. site formation of about 70 hectares ("ha") of land (including soil treatment works) in the KTN and FLN NDA;
  2. construction of the Fanling Bypass (Eastern Section) of about 4 kilometres ("km") long, which is a dual two‐lane carriageway connecting the FLN NDA to Fanling Highway, about 10 km of local roads and about 10 km of footpaths, and about 4 km cycle tracks within the NDA area, and associated junction/road improvements;
  3. engineering infrastructure works including drainage, sewerage (including two sewage pumping stations), waterworks (including a fresh water service reservoir of about 27 500 cubic metres ("m3") capacity and a flushing water service reservoir of about 11 500 m3 capacity in the KTN NDA), landscaping works and slopeworks;
  4. part expansion and upgrading of Shek Wu Hui Sewage Treatment Works ("SWHSTW") to increase its treatment capacity by 20 000 m3 per day;
  5. reprovisioning works; and
  6. implementation of environmental mitigation measures and environmental monitoring and audit ("EM&A") programme for the works mentioned in paragraphs (a) to (e) above.

Project Office in Civil Engineering and Development Department:

North Development Office (Enquiry: 3547 1615)

Consultant:

AECOM Asia Company Limited

Approved Project Estimate:

$17.32 Billion

Related Website:

http://ktnfln-ndas.gov.hk/en/index.php

Current Progress:

Construction commenced in September 2019

Contract:

 Contract no. ND/2019/06

Scope:

The contract mainly comprises construction of an in-situ reprovisioned NDTWM and its facilities involving a steel canopy for the trading area and a management office building.

Commencement Date:

27 September 2019

Completion Date:

mid 2021

Contract Sum:

$162 million

Contractor:

New Concepts Engineering Development Limited

 Contract No. ND/2019/01

Scope: 

The works mainly comprise site formation of land under the First Phase of KTN NDA (including soil treatment works); construction of engineering infrastructures including drainage works, sewerage works (including temporary sewage treatment facilities), waterworks (including a fresh water service reservoir and a flushing water service reservoir), roadworks (including carriageway, footpaths, cycle tracks, a subway and junction improvement), pipeworks for district cooling system, slope works and landscaping works; and construction of associated environmental mitigation works including noise barriers/noise enclosures and low noise road surfacing.

Commencement Date: 6 December 2019
Completion Date: early 2026
Contract Sum: $2.578 Billion
Contractor: Build King - Richwell Engineering Joint Venture

Contract No. ND/2019/02

Scope: The contract mainly comprises road and drainage works between Kwu Tung North New Development Area and Shek Wu Hui; construction of a sewage pumping station, a visitor centre for Long Valley Nature Park and a footbridge spanning across Sheung Yue River; and site formation of land and the associated engineering infrastructure works for a village resite area in Kwu Tung North New Development Area.
Commencement Date:
17 February 2020
Completion Date:
end 2024
Contract Sum:
$598 million
Contractor:
Chun Wo - Kwan Lee Joint Venture

Contract No. ND/2019/05

Scope:

The contract mainly comprises construction of an approximately 2 kilometres (km) long dual two-lane Fanling Bypass Eastern Section between Shung Him Tong and Kau Lung Hang mainly on viaducts with two long span overbridges across the existing East Rail Line; realignment of part of the existing Tai Wo Service Road East, Tai Wo Service Road West and Fanling Highway;  construction of approximately 2.4 km long noise barriers, and relocation of approximately 400 metres long existing noise barriers along Fanling Highway;  alteration and addition works to the existing Ho Ka Yuen footbridge; reprovisioning of a bus-bus interchange at Fanling Highway with a proposed public toilet and covered walkway; and associated slope works, ground investigation, geotechnical instrumentation and monitoring, retaining wall, drainage works, waterworks, sewerage works, traffic control and surveillance system installation, electrical and mechanical works and landscaping works.

Commencement Date: 2 March 2020
Completion Date: early 2025
Contract Sum: $2.268 Billion
Contractor: CRCC – Paul Y. Joint Venture