Improvement to So Kwun Po Interchange

Project Number:

7086TI

Brief Description of Project Scope:

The works mainly comprise:-

  1. construction of north-south link road of about 700m connecting Pak Wo Road and San Wan Road;
  2. reconstruction of sections of So Kwun Po Road near North District Park;
  3. widening of the north-western slip road from So Kwun Po Road to San Wan Road;
  4. reconstruction and realignment of So Kwun Po Road between Kai Leng Roundabout and Pak Wo Road;
  5. improvement works at the junction of San Wan Road and the proposed north-south link road;
  6. improvement works at the junction of Pak Wo Road and So Kwun Po Road;
  7. construction of a lift and a staircase linking San Wan Road and elevated So Kwun Po Road;
  8. construction of a pedestrian subway across So Kwun Po Road near Pak Wo Road;
  9. re-provision of the roller skating rink within North District Park affected by the road works; and
  10. associated works including geotechnical, landscape, drainage, water, installation of noise barriers, electrical and mechanical, environmental mitigations, street lighting and utilities works, as well as installation of street furniture and traffic aids.

Project Office in Civil Engineering and Development Department:

North Development Office

Consultant:

WSP (Asia) Limited

Current Progress:

Investigation and design works commenced in September 2021.

Other Related Information:

Gazette Date Subject
07 June 2024 and 14 June 2024
Authorization of Scheme

25 August 2023 and 1 September 2023 Scheme