Site Formation and Infrastructure Works for Public Housing Development at A Kung Ngam Village, Eastern

Project Number:

B880CL
Attachment 1

Brief Description of Project Scope:

The scope of the project mainly comprises:

(a) Site formation works including site clearance and land decontamination works (if required);

(b) Geotechnical works including slope works, natural terrain hazard mitigation measures and construction of retaining structures;

(c) Demolition Works including unnamed industrial building (Handling of asbestos containing materials may be required);

(d) Roadworks;

(e) Waterworks;

(f) Drainage and Sewerage Works;

(g) Associated Tree Felling, transplanting and Preservation Works; and

(h) Ancillary Works including waterworks, landscape works and environmental mitigation measures.


Project Office in Civil Engineering and Development Department:

Civil Engineering Office

Consultant:

WSP (Asia) Limited

Approved Project Estimate:

$572.3 million

Current Progress:

The works commenced on 13 May 2025.

Contract:

Contract No.:  SD/2024/01

Scope:  Same as project scope

Contract Sum:  $442.2 million

Contractor:

Sang Hing - Kuly Joint Venture

Other Related Information:

Gazette Date Subject
10 Nov 2023 Authorization of Scheme
4 Aug 2023 & 11 Aug 2023 Scheme
4 Aug 2023 & 11 Aug 2023 Scheme