Yuen Long South Development – Second Phase Development
Project Number:
7906CLBrief Description of Project Scope:
Second Phase development (also known as Stage 2B works) mainly covers –
(a) site clearance and formation (including land decontamination works) of about 63 ha of land together with the provision of associated engineering infrastructure, to ready these formed land for subsequent development of public housing, community facilities, multi-storey buildings for brownfield operations, open storage, village resite areas and Yuen Long South Effluent Polishing Plant, and for construction of the proposed infrastructure works in paragraph (b) below;
(b) engineering infrastructure works including improvement works to Tin Shui Wai West Interchange, local roads, sewerage system (including pumping stations), drainage facilities, water supply facilities, reclaimed water facilities, landscaping, electrical and mechanical ("E&M") and associated works; and
(c) environmental mitigation measures and the EM&A programme for the works in paragraphs (a) and (b) above.
Project Office in Civil Engineering and Development Department:
West Development Office (Enquiry: 2158 5680)Consultant:
Agreement No. CE 16/2022 (CE) - "Yuen Long South development – stages 2B and 3 works - Design and Construction"- AECOM Asia Company Limited
Approved Project Estimate:
$ 13,764.6 millionRelated Website:
https://www.yls.hk/Current Progress:
Works commenced progressively from September 2025.
Contract:
Contract No. YL/2024/02 - Yuen Long South New Development Area Second Phase Development- Contract 4 - Site Formation and Engineering Infrastructure Works
| Scope: | (a) site clearance and formation (including land decontamination works), together with the provision of associated engineering infrastructure; (b) construction of a retention pond; (c) construction of one nullah decking and three footbridges across Yuen Long Nullah; (d) re-alignment and widening of sections of existing Kung Um Road and Pak Sha Shan Road; (e) construction of associated works including junction improvement works, cycle tracks, footpaths, water supply system, sewerage system, drainage system, box culverts, slope works, retaining walls, landscaping works, electrical and mechanical works and other ancillary works; and (f) implementation of environmental mitigation measures for the works mentioned above. |
| Commencement Date: | 8 September 2025 |
| Completion Date: | 2030 |
| Contract Sum: | $936 million |
| Contractor: | Build King – Richwell Civil Joint Venture |