Boardwalk underneath Island Eastern Corridor
Project Number:
7873THBrief Description of Project Scope:
The works mainly include:
(a) construction of a boardwalk of about 2.2 kilometres (km) long and at least 10 metres (m) wide (including a passage of about 0.4 km within the existing North Point Promenade) for different users, the access points to the hinterland, viewing platforms, and fishing platform;(b) construction of movable bridges;
(c) provision of ancillary facilities with architectural features such as shelters, glass balustrades, seating, water dispensers, toilets, kiosks, as well as a management office and a function room at Hoi Yu Street;
(d) implementation of beautification, modification and revitalisation works of existing facilities to be affected along the proposed Boardwalk, such as the North Point Promenade, Tong Shui Road Pier, North Point Vehicular Ferry Pier, Hoi Yu Street and IEC structures;
(e) implementation of associated road, drainage, sewerage, electrical and mechanical (E&M), waterworks, landscaping works and other ancillary works; and
(f) implementation of environmental mitigation measures and an environmental monitoring and audit (EM&A) programme for the works mentioned in items (a) to (e) above.
