Site formation and infrastructure works for public housing development at Ka Wai Man Road and Ex-Mount Davis Cottage Area, Kennedy Town

Project Number:

B766CL
Attachment 1

Brief Description of Project Scope:

The public housing development will be implemented in two phases providing about 2 340 public housing units to accommodate about 7 500 people.  The Civil Engineering and Development Department will carry out site formation and infrastructure works for Phase 2 of the development including associated slope improvement works, construction of an access road leading to the Phase 2 of the development via Victoria Road, and construction of a footbridge connecting the public housing development and Ka Wai Man Road to Victoria Road. 

Project Office in Civil Engineering and Development Department:

South Development Office (Enquiry: 3842 7062)

Consultant:

Black & Veatch Hong Kong Limited

Current Progress:

The detailed design of site formation and infrastructure works is on-going.

Other Related Information:

Scheme / Amendments of Scheme / Authorization of Scheme
Gazette Date Subject
16 Nov 2018 &
23 Nov 2018

Authorization of Scheme

22 Jun 2018 &
29 Jun 2018

Scheme