Home > Completed Major Projects > Kowloon >Kai Tak development – stage 2 infrastructure at north apron area of Kai Tak Airport

Completed Major Projects

7746CL
Kai Tak development – stage 2 infrastructure at north apron area of Kai Tak Airport
Kai Tak development – stage 2 infrastructure at north apron area of Kai Tak Airport

Brief Description of Project Scope:

  1. construction of about 590 metres (m) of new roads and 2110 m of footpaths;
  2. construction of drainage box culverts of total length of about 1565 m;
  3. construction of a sewage pumping station;
  4. associated utility, drainage, sewerage, water mains and landscape works; and
  5. provision of necessary environmental mitigation measures and implementation of an environmental monitoring and audit (EM&A) programme associated with the above works.

Cost:

$355.8 million


Completion Date:

June 2015

Project Office in Civil Engineering and Development Department:

Kowloon Development Office (Enquiry: 2301 1486)