Brief Description of Project Scope:

  1. construction of approximately 1.8 km long single 2-lane carriageway and associated footpaths and landscaping works;
  2. improvements to the former taxiway bridge, existing roads and junctions;
  3. construction of a fireboat berth cum public landing steps together with access road;
  4. construction of storm drains, sewers and water mains;
  5. construction of a sewage pumping station; and
  6. provision of necessary environmental mitigation measures and implementation of an environmental monitoring and audit programme associated with the above works.

Cost:

$540 million


Completion Date:

September 2012