Home > On-going Projects > Major Projects > Under Construction > Territory-wide > Cycle Tracks Connecting North West New Territories with North East New Territories – Tuen Mun to Sheung Shui section (Stage 1)

On-going Projects

7279RS
Cycle Tracks Connecting North West New Territories with North East New Territories – Tuen Mun to Sheung Shui section (Stage 1)
Cycle Tracks Connecting North West New Territories with North East New Territories – Tuen Mun to Sheung Shui section (Stage 1)

Brief Description of Project Scope:

The project forms part of the NT Cycle Track Network which connects local cycle track networks in various new towns and is mainly for recreation purpose. The works under this project comprise the construction of approximately 2.5 km new cycle tracks in Yuen Long and Sheung Shui, improvement works to about 4.5 km in length of selected sections of existing cycle tracks in Tuen Mun, Tin Shui Wai and Yuen Long together with the provision of supporting facilities.


Approved Project Estimate:

$295.4 million


Current Progress:

Cycle tracks already open to public.


Project Office in Civil Engineering and Development Department:

West Development Office (Enquiry: 2417 6367)


Consultant:

AECOM Consulting Services Limited


Contract:

Contract No. YL/2013/01
Scope: Construction of approximately 2.5 km new cycle tracks along Kam Tin River in Yuen Long and along Shek Sheung River and Sheung Yue River in Sheung Shui, improvement works to about 4.5 km in length of selected sections of existing cycle tracks in Tuen Mun, Tin Shui Wai and Yuen Long and construction of entry/exit hubs and resting stations along the cycle tracks.
Commencement Date: 29 November 2013
Completion Date: 2016
Contract Sum: $193.85 million
Contractor: Sang Hing – Kuly Joint Venture