Brief Description of Project Scope:
This project consists of about 1 km of road tunnel and the Sha Tin toll plaza formation together with connecting roads to Road T3 and slip roads to Che Kung Miu Road.
Current Project Progress:
The project has been substantially completed and the roads were opened to the public on 21 March 2008.
Contract:
Contract No. ST89/02
Scope (a) site formation, drainage, geotechnical and landscape works for the toll plaza;
(b) construction of approximately 1 km of 3-lane twin-bore tunnel underneath Sha Tin Heights;
(c) construction of a dual 2-lane at-grade carriageway of about 0.7 km linking the Sha Tin Heights Tunnel and Road T3;
(d) construction of slip roads connecting to Che Kung Miu Road; and
(e) construction of noise mitigation measures.

Commencement Date Nov 2002
Completion Date September 2007
Estimated Value $1195 million
Current Progress The works are substantially completed
Contractor Mr. C. Y. Mak
China State - China Railway Joint Venture
Telephone: 2601 7982
Resident Engineer Mr. David Kwan, AECOM Asia Company Limited
Chief Resident Engineers Office
7900 Tai Po Road, Sha Tin Heights
New Territories
Telephone: 2697 4683
Contact:
CEDD
Suite 1213 Chinachem Golden Plaza, 77 Mody Road, Tsim Sha Tsui East, Kowloon
Mr. MA Siu Man (Tel :23011383)
Consultants
AECOM Asia Company Limited