Brief Description of Project Scope:

This project will enhance the existing infrastructure to cater for the public housing development in Area 16 and Area 58D, Sha Tin. The project comprises:

  1. Widening and realignment of a section of Kwei Tei San Chuen Road between Wong Chuk Yeung Street and the public light bus terminus in front of Kwai Tei New Village;
  2. Widening a section of Wong Chuk Yeung Street between Kwei Tei San Chuen Road and Wo Sheung Tun Street; and
  3. Carrying out ancillary works including civil, structural, geotechnical, landscaping and streetscaping works and environmental protection and mitigation measures, for completion of the above items nos. (a) and (b).


Approved Project Estimate:

About $224 million


Current Progress:

Construction works commenced on 17 March 2016. Cut slope works, slope upgrading works and roadworks are in progress.

Project Office in Civil Engineering and Development Department:

North Development Office (Enquiry: 2301 1400)


Consultant:

Atkins China Limited


Contract:

Contract No. NE/2015/09
Scope: Widening and realignment of a section of Kwei Tei San Chuen Road, widening a section of Wong Chuk Yeung Street and ancillary works including cut slope, fill slope, retaining wall and upgrading of slopes.
Commencement Date: 17 March 2016
Completion Date: end 2018
Contract Sum: $93 million
Contractor: Ming Shing Construction Engineering Company Limited