Home > On-going Projects > Major Projects > Under Planning > New Territories > Cross Bay Link, Tseung Kwan O

On-going Projects

7822TH
Cross Bay Link, Tseung Kwan O
Cross Bay Link, Tseung Kwan O

Brief Description of Project Scope:

Cross Bay Link will connect Tseung Kwan O – Lam Tin Tunnel to Wan Po Road near Area 86 to cope with the anticipated traffic demand in Tseung Kwan O. It will divert industrial traffic from the town centre so as to improve the living environment of the residential areas. The project includes an approximately 1.8 kilometres long dual two-lane carriageway with a cycle track and a footpath across Junk Bay mainly on viaduct, with the necessary slip roads and junction improvements.


Related Website:

http://www.cbltko.hk/en/

Current Progress:

The Environmental Impact Assessment (EIA) report was approved by Director of Environmental Protection (DEP) under the EIA Ordinance on 11 July 2013 and the associated Environmental Permit was granted by DEP on 15 August 2013.

The project was authorized by the Chief Executive in Council (the relevant notice was published on 21 November 2014).

The consultancy assignment for design and construction of the project commenced in August 2014.

The site investigation works for detailed design stage of the project was completed in November 2015.

Wind tunnel tests are in progress.

Project Office in Civil Engineering and Development Department:

East Development Office (Enquiry: 2301 1504)


Consultant:

AECOM Asia Company Limited.