7756CL
Ma On Shan Development – Roads, Drainage and Sewerage Works at
Whitehead and Lok Wo Sha, Phase 2
Ma On Shan Development – Roads, Drainage and Sewerage Works at <br/>Whitehead and Lok Wo Sha, Phase 2

Brief Description of Project Scope:

The project will provide additional infrastructure to support various planned developments at Whitehead. The project comprises:

  1. widening of Yiu Sha Road from a single two-lane to a dual two-lane road of about 500 metres (m) long, and construction of associated retaining walls, footpaths, cycle tracks and amenity areas;
  2. construction of a covered footbridge with lift across Yiu Sha Road;
  3. construction of a sewage pumping station and sewers; and
  4. ancillary works including storm drains, water mains, landscaping and utility works.

Approved Project Estimate:

About $253 million


Current Progress:

Construction of road works, footbridge, sewage pumping station, retaining walls and underground utilities are in progress.

Project Office in Civil Engineering and Development Department:

North Development Office (Enquiry: 2301 1400)


Consultant:

Ove Arup & Partners Hong Kong Limited


Contract:

Contract No.: NE/2014/05
Scope: Widening of Yiu Sha Road, construction of a covered footbridge with lift, a sewage pumping station and sewers and ancillary works
Commencement Date: 24 July 2015
Completion Date: early 2018
Contract Sum: $155 million
Contractor: CMGC-TECEL Joint Venture