5019GB
Liantang/Heung Yuen Wai Boundary Control Point and associated works - site formation and infrastructure works
Liantang/Heung Yuen Wai Boundary Control Point and Associated Works

Brief Description of Project Scope:

The project mainly comprises site formation of about 23 hectares of land for provision of Boundary Control Point (BCP) buildings and associated facilities, construction of about 11km long dual 2-lane Connecting Road linking up the BCP with Fanling Highway, design and construction of the Hong Kong Special Administrative Region portion of vehicular bridges and pedestrian bridge crossing Shenzhen River, associated diversion/modification works at existing local roads and junctions, drainage, sewerage, waterworks and landscaping works.


Approved Project Estimate:

$25.0 billion


Related Website:

http://www.lthywbcp.com.hk


Current Progress:

Construction commenced in April 2013


Project Office in Civil Engineering and Development Department:

New Territories East Development Office (Enquiry : 3547 1631)


Consultant:

AECOM Asia Co. Ltd.


Contract:

Contract No. CV/2012/08
Scope: The works include construction of a dual two-lane trunk road (with about 0.4km of at-grade road and 4.8km of tunnel) connecting the Fanling Interchange with the Sha Tau Kok Interchange, tunnel administration building and ventilation buildings, provision and installation of ventilation system, E&M works and building services, associated landscaping works, drainage / sewerage, waterworks, utilities and traffic engineering works.
Commencement Date : 20 December 2013
Completion Date : mid to end 2018
Contract Sum : $10.314 billion
Contractor : Dragages Hong Kong Limited

Contract No. CV/2012/09
Scope: The works include the construction of an interchange with four viaducts near Kiu Tau, Fanling for the connecting road to the Boundary Control Point, widening of a section of the Fanling Highway of about 1 km long near the interchange, demolition of the existing Kiu Tau Vehicular Bridge, re-provisioning of the existing Kiu Tau Footbridge, realignment of the existing Tai Wo Service Road West and Tai Wo Service Road East, and associated slope, drainage, sewerage, water, and landscape works.
Commencement Date : 31 July 2013
Completion Date : Mid 2018
Contract Sum : $2.545 billion
Contractor : Chun Wo Construction and Engineering Company Limited

Contract No. CV/2013/03
Scope: The works include site formation of about 23 hectares of land for the development of the new BCP, diversion/modification of Lin Ma Hang Road, associated drainage, sewerage, waterworks, utilities and landscaping works.
Commencement Date :

11 April 2013

Completion Date : 9 January 2016
Contract Sum : $510 million
Contractor : Sang Hing Civil - Richwell Machinery JV

Contract No. CV/2013/08
Scope: The works include construction of a 4.6 km long dual two-lane trunk road (with about 0.6km at grade roads, 3.3km viaducts and a 0.7km tunnel) connecting Sha Tau Kok Road Interchange to BCP, and the associated environmental mitigation measures, landscaping, drainage/sewerage, waterworks and utilities works.
Commencement Date :

24 June 2015

Completion Date : End 2018
Contract Sum : $6,518 million
Contractor : CRBC-CEC-KADEN Joint Venture

Contract No. NE/2014/02
Scope: The works mainly include design, supply, delivery, installation, testing and commissioning of a traffic control and surveillance system for the connecting road linking up the Liantang/Heung Yuen Wai Boundary Control Point and the existing Fanling Highway. The system will mainly consist of computer systems, communication facilities, variable message signs and other traffic field equipment.
Commencement Date :

27 April 2016

Completion Date : Early 2021 (Major part of the works will be completed by end 2018)
Contract Sum : $337 million
Contractor : Siemens Limited

Contract No. NE/2014/03
Scope: The works include construction of the Hong Kong Special Administrative Region portion of four vehicular bridges and one pedestrian bridge crossing Shenzhen River.
Commencement Date :

11 December 2015

Completion Date : End 2018
Contract Sum : $462 million
Contractor : Kwan On-Richwell-SCG JV


Environmental Monitoring and Audit Information:

http://www.lthywbcpema.com