Home > On-going Projects > Major Projects > Under Construction > Kowloon > Development at Anderson Road

On-going Projects

B566CL
Development at Anderson Road
Development at Anderson Road

Brief Description of Project Scope:

Construction of site formation, roads, drains and upgrading of existing infrastructure to provide usable land of about 20 hectares for housing and associated government, institution or community uses at the site between existing Anderson Road Quarry and Sau Mau Ping Road in Kwun Tong District.


Approved Project Estimate:

$3.4 billion


Current Progress:

Construction commenced on 31 January 2008.


Project Office in Civil Engineering and Development Department:

Civil Engineering Office


Consultant:

Ove Arup & Partners Hong Kong Limited


Contract:

Contract No. CV/2007/03
Scope: Construction of site formation, roads, drains and upgrading of existing infrastructure to provide usable land of about 20 hectares for housing and associated government, institution or community uses at the site between existing Anderson Road Quarry and Sau Mau Ping Road in Kwun Tong District.
Commencement Date: 31 January 2008
Completion Date: End 2016
Contract Sum: $2.8 billion
Contractor: China State Construction Engineering (Hong Kong) Limited

Contract No. CV/2012/07
Scope: Construction of a footbridge and associated lift towers across Shun On Road between Shun Tin Estate and the future development platform at +152mPD.
Commencement Date: 31 January 2013
Completion Date: End 2016
Contract Sum: $152 million
Contractor: Lam-Po Wing Joint Venture


Environmental Monitoring and Audit Information:

http://www.anderson-road.com/