7731CL
Infrastructure works for housing sites adjacent to Lung Ping Road at Tai Wo Ping, Shek Kip Mei
Brief Description of Project / Study Scope:
- construction of a single two-lane road of about 0.45 kilometre (km) long on bridge structures (Bridges Nos. 2 to 4) and at-grade connecting the vehicular ingress/ egress point of Site No. LS-SSP-0013 with the westbound carriageway of Lung Cheung Road;
- construction of two single lane roads of total length about 0.53 km on bridge structure (Bridge No. 1) and at-grade connecting the eastbound carriageway of Lung Cheung Road and the abovementioned proposed single two-lane road;
- geotechnical works, including slope stabilisation works, check dam and retaining walls;
- ancillary works including associated footpaths, vehicle ingress/egress points, drainage, sewerage, water mains and landscaping works; and
- provision of necessary environmental mitigation measures and implementation of an environmental monitoring and audit programme associated with the above works.
Approved Project Estimate:
$781 million
Current Progress:
Works commenced on 31 July 2013 and are on schedule.
Project Office in Civil Engineering and Development Department:
South Development Office (Enquiry: 2301 1486)
Consultant:
Mott MacDonald Hong Kong Ltd
Contract:
Contract No. KL/2011/02
Scope: | same as project scope above |
Commencement Date: | 31 July 2013 |
Completion Date: | end 2016 |
Contract Sum: | $576 million |
Contractor: | Penta-Ocean Construction Co., Ltd. |