7677CL
Wan Chai development phase II, engineering works
Plan 1 Wan Chai Development Phase II - Engineering Works(Extent Of Reclamation And Underground Facilities) Plan 2 Wan Chai Development Phase II - Engineering Works(Extent Of Reclamation And Underground Facilities) Plan 3 Wan Chai Development Phase II - Engineering Works(Roads And Above-Ground Facilities)

Brief Description of Project Scope:

The scope of the project comprises:

  1. reclamation of the seabed in Wan Chai North and North Point to form a total of about 12.7 ha of land, including construction of about 1.57 km of seawall;
  2. construction of precast box structures spanning over the existing Mass Transit Railway (MTR)Tsuen Wan Line;
  3. construction of ground level roads of about 0.7 km in total length, modification of existing roads for connection with the slip roads of the proposed Trunk Road, and some other road junction improvement works;
  4. extension of a dual two-lane primary distributor, Road P2, and realignment of the existing Convention Avenue and Hung Hing Road, of about 1.0 km in total length;
  5. relocation of a public transport interchange (PTI) at Expo Drive East to combine with an existing PTI at Wan Chai North;
  6. construction of a footbridge of about 180 m in length along Wan Shing Street;
  7. construction of three pedestrian landscaped decks to the west of Hong Kong Convention and Exhibition Centre (HKCEC), the north of the Wan Chai North PTI and the north of Victoria Park;
  8. construction of stormwater box culverts of about 1.17 km in total length in Wan Chai North and North Point and the associated hinterland drainage improvement works;
  9. reprovisioning of existing waterfront facilities including cross harbour water mains, submarine sewage outfall pipelines, ferry piers, cooling water pumping systems and a salt water pumping station;
  10. construction of associated footpaths, roadside amenities, stormwater drainage works, sewerage works and landscaping works; and
  11. implementation of environmental mitigation measures, and an environmental monitoring and audit (EM&A) programme for the works mentioned above.


Approved Project Estimate:

$4.643 billion


Related Website:

http://www.wd2.gov.hk


Current Progress:

The construction works for WDII commenced in December 2009. . The WDII works at Wan Chai would be implemented under six CEDD works contracts. Four works contracts were awarded since end 2009 and two of them were substantially completed in July 2013 and May 2016. The implementation plan of the remaining two works contracts would be determined to dovetail with the planning and developments in the Wan Chai areas.

The reprovisioning works required for the land formation have been completed and commissioned, including the permanent government helipad, WSD’s salt water pumping station, new Wan Chai Ferry Pier and cooling water pumping systems.

In December 2015, the land formation works for the construction of Central-Wan Chai Bypass (CWB) were completed. Sections of the CWB tunnel structures at Hong Kong Convention and Exhibition Centre and Wan Chai East have been handed over to Highways Department (HyD) for carrying out subsequent works. Construction of remaining sections of CWB tunnel structures within the project area is in full swing. Furthermore, some land parcels have also been handed over to HyD for the construction of Shatin-Central Link (SCL). The road works necessary for enabling the commissioning of the Central – Wan Chai Bypass would be completed in the first quarter of 2018.

Project Office in Civil Engineering and Development Department:

South Development Office (Enquiry: 2301 1486)


Consultant:

AECOM Asia Company Limited


Contract:

Contract No. HK/2009/01
Scope: The works mainly include land formation and construction of the Central-Wan Chai Bypass tunnel at the water channel in between the two phases of Hong Kong Convention and Exhibition Centre and other associated works.
Commencement Date: 30 December 2009
Completion Date: May 2016
Contract Sum: $2.314 billion
Contractor: Chun Wo - Leader Joint Venture

Contract No. HK/2009/02
Scope: The works mainly include land formation and construction of the Central-Wan Chai Bypass at Wan Chai East and other associated works.
Commencement Date: 28 January 2010
Completion Date: Q3 2018 (estimated)
Contract Sum: $3.359 billion
Contractor: Chun Wo - CRGL Joint Venture

Contract No. HK/2012/08
Scope: The works mainly include land formation and construction of the Central-Wan Chai Bypass at Wan Chai West and other associated works.
Commencement Date: 31 January 2013
Completion Date: Q1 2018 (estimated)
Contract Sum: $3.350 billion
Contractor: China State – Build King Joint Venture

Contract No. HK/2010/06
Scope: The works mainly include land formation and construction of the Central-Wan Chai Bypass over MTR Tsuen Wan Line tunnel
Commencement Date: 20 January 2011
Completion Date: July 2013
Contract Sum: $705 million
Contractor: Gammon - Leader Joint Venture

Environmental Monitoring and Audit Information:

http://www.wd2-cwb.com/